BUILD PHASE
ACTIVITY & TASKS
Site Setup
Goal Date: SEPT 29th (completed)
- Site Setup
- SURVEY FOUNDATION POINTS - Appointment: Sept 24th
DEMOLITION
Start Date: Sept 15th
Goal Date: OCT 2nd (on target)
Grading/Lot Clearing
Start Date: SEPT 29th
Goal Date: SEPT 30th (completed)
- Debris Removal & Clearing
- Grade
- Schedule Raleigh Inspection for soil check Goal Date: SEPT 29th by 4PM
Concrete & Masonry
Start Date: SEPT 30th
Goal Date: OCT 8th (completed)
- FOUNDATION MATERIALS Delivered - Delivery Date Sept 29th
- Concrete Block
- Brick
- Sand
- Purchase Bolts, vent lentels (Custom Brick), Vents (HomeDepot)
- DIG FOOTINGS
- Order 4 yards of concrete for footings
- POUR FOOTINGS
- 1st TERMITE TREATMENT (FLUME AREA ONLY) - Appointment: Oct 1st, 8AM
- POUR FLUME
- SET BRICK POINTS
- FOUNDATION WALLS (BLOCK & BRICK)
- 2nd TERMITE TREATMENT Foundation
- WATERPROOF FOUNDATION
- BACKFILL FOUNDATION
Framing
Start Date: OCT 9th
Goal Date: OCT 15th (completed)
- FRAMING MATERIALS Delivered - Goal Date: Oct 8th (COMPLETED)
- Only do FRAME FLOOR SYSTEM/JOISTS before inspection
- Schedule Raleigh Inspection for foundation and floor system Goal Date: OCT 9th by 4PM
- apply underlayment
- frame walls
- apply exterior sheathing
- house wrap
- roof felt
WINDOWS * DOOR OPENINGS
Start Date: Oct 9th
Goal Date: Oct 21th (completed)
- WINDOWS Delivered Oct 9th
- Exterior Doors Delivered Oct 13th
- Purchase Exterior Trim (HomeDepot)
- Install windows
- Install Exterior Doors
- Install exterior trim
EXTERIOR FINISHING
Start Date: Oct 21st
Goal Date: Nov 7th (on target)
- Install FASCIA boards ONLY before roof
- NO SOFFIT
- Order hardie Board
- Install SIDING
ROOFING
Goal Date: Oct 22nd (completed)
- Order/Pickup Materials
- Squares of Roofing (6 - 7)
- Drip Edge, Flashing, Hardware (HomeDepot)
- Material Reference
ROUGH-IN ELECTRIC
Goal Date: Nov 1st (on target)
- Circuit Panel
- Electric Wire, Boxes
ROUGH-IN PLUMBING
Goal Date: Nov 1st (on target)
- Waste
- Water
ROUGH-IN HEAT & A/C
Start Date: Oct 28th
Goal Date: Nov 1st (on target)
- Ducts & Vents
- Bath Fans & Vents
- Dryer Vent
INSULATION
- Walls
DRYWALL
- Hang
- Tape
- Block & Skim Coats
- Sand
- Clean Up
WOOD FLOORS
- Install
- Sand, Seal, Stain
- Finish Coat
EXTERIOR PAINT
INTERIOR PAINT
TRIM CARPENTRY
- Interior Doors
- Base
- Casing Trim
- Window Stool
- Closet Shelving
- Decorator Mouldings, Etc.
- Finish Hardware, Mirrors, Etc.
CABINETS-VANITIES-TOPS
Cabinets, Bath Vanities
Bath Vanity Tops
Medicine Cabinets
GUTTER & DOWN SPOUT
Stormwater Control
FINISH GRADING
CERAMIC TILE
Backer Board & Prep
Tile & Grout
ELEC-SWITCH/PLUG/PANEL
VINYL FLOORING
Subfloor
Square Yards of Vinyl
APPLIANCES
Purchase & Delivery
Installation
HEATING & A/C
Install & Test Equipment
Grills & Thermostat
PLUMBING TRIM
ELECTRICAL TRIM
FINAL CLEAN
WALK THROUGH
FINISH PUNCH LIST
DRIVEWAY REMOVAL
Grade
Base Rock, Culverts